TESTING
All our products undergo stringent testing to IEC EN
60439 standards before leaving our premises including:
|
- A visual survey ensures correct placing of all
components, and that all live conductors are shrouded
to prevent accidental personal injury. This survey
will also ensure that all signs and labels requested
by the customer are in place and that all necessary
parts and instructions for assembly are dispatched
with the panel.
- A mechanical inspection checks the quality of mechanical
items including hand operated devices and mechanical
interlocks. During this inspection, all electrical
connections are torqued as per the manufacturers’
recommendations and all wiring to doors and live conductors
are mechanically protected.
- An electrical inspection tests the main instrument
circuits, including a functioning test of the control
circuit and the wiring and PLC, if appropriate.
- A high voltage test will also be carried out to
maximum of 4KV (2.5kv for 1 minute recommended).
Photographs are taken of each board and are archived
with the final as-built drawings.
If required, we will carry out commissioning and final
testing on site.
|
Photographs are taken of each board
and are archived with the final as-built drawings. If required,
we will carry out commissioning and final testing on site.
|